Summary

Premise Engineering was appointed by our client, Jellinbah Coal, to undertake design and construction supervision of a de-watering, ‘regulated structure’ dam for their Central Operations. This significant upgrade would mean the dam, west of Rockhampton, offered 1.5 gigalitres in capacity and spanned a total area of 32 hectares.

The Jellinbah Dam was constructed behind the existing high-wall. Our design brief was multifaceted, and needed to address:

  • De-watering storage for the surrounding coal mine site
  • Compliance issues relating to mine inspections and water licences
  • Safeguards to protect existing mine site infrastructure in case of major rain
  • Provisions for spillways, water release and metering in major rain events
      • Despite challenges, such as constructing the dam wall during Queensland’s wet season, Premise Engineering was able to design and deliver a successful project for our client. We are proud to have met such a rigorous brief, and to have completed the Jellinbah Dam upgrade on schedule.